6 min read

The Data Center Power Fight Is Moving From Policy to Grid Operations

New federal records show how regulators are tracking large electricity users, allocating grid costs and preparing for emergencies.
The Data Center Power Fight Is Moving From Policy to Grid Operations
Photo by American Public Power Association / Unsplash

New federal records preserved by 337.NEWS show regulators converging on three questions: how giant new electricity users are tracked, who pays for the power infrastructure they require, and what happens when the grid itself runs short.

For most of the data-center boom, the electricity debate has sounded theoretical.

How much power will these facilities actually consume? Who will build the generation? Who pays for new transmission lines? Will ordinary customers eventually absorb some of those costs?

A new collection of federal records added to the 337.NEWS Louisiana Public Records Repository shows that those questions are beginning to move out of policy papers and into actual grid operations.

The archive contains 25 files totaling roughly 6.8 MB, pulled from the U.S. Department of Energy, Federal Energy Regulatory Commission, PJM Interconnection, the White House and related federal sources.

Taken together, they document something larger than any single filing.

The federal government is beginning to build an operating framework for extremely large electricity users — particularly data centers — based around three ideas:

Track them. Make them pay for the infrastructure required to serve them. And, when the grid approaches an emergency, make use of the power resources sitting behind their meters.

DOE just exercised emergency grid authority

On October 12, Energy Secretary Chris Wright issued DOE Order No. 202-26-50 under Section 202(c) of the Federal Power Act.

The order applies to PJM Interconnection, the massive regional grid operator serving portions of 13 states and the District of Columbia.

It was not issued specifically because of data centers.

PJM sought emergency authority during a period of elevated demand combined with significant planned generator and transmission outages associated with the fall maintenance season.

But the mechanism DOE authorized is important.

From October 13 through October 16, PJM was authorized to dispatch specifically identified generating units when necessary to maintain reliability.

The order went further.

PJM was also authorized, as a last resort before declaring the most severe level of grid emergency — an Energy Emergency Alert 3 — or during such an emergency, to direct backup generation resources to operate.

That includes auxiliary and standby generators, directly connected generation, battery storage and other backup resources.

PJM subsequently described the provision in an operational notice as applying to backup generators at large loads.

That is a notable change in the relationship between giant electricity consumers and the grid.

A data center's backup generator is normally thought of as equipment protecting the data center from the electric system.

Under DOE's emergency framework, that equipment can also become a resource protecting the electric system from the data center's demand.

There are limits.

Critical facilities such as hospitals, 911 centers, defense facilities, water and wastewater systems and similar essential operations are exempted from the backup-generation provision.

The emergency order also does not mean PJM can simply run every available generator continuously. Operations must still be tied to reliability needs.

PJM said October 13 that it expected to need identified resources for the October 14 operating day. By the following evening, however, PJM said it did not expect to need those resources beginning October 15 through the end of the order, and that the emergency conditions were not expected to continue past October 14.

So this was not a prolonged emergency.

What matters is that the mechanism now exists — and has been formally exercised.

FERC drew a line around a “Large Load”

Three days earlier, another important piece fell into place.

On October 9, FERC issued its order in Docket ER26-3515-000, concerning PJM's proposed Interim Resource Adequacy Service, or IRAS.

PJM had proposed a broader set of rules for handling massive new electricity loads.

FERC rejected much of that proposal.

But it did not reject everything.

The Commission accepted PJM's definition of a Large Load as 50 megawatts or more at a single site and approved creation of a Large Load Registry, effective October 12.

That distinction matters.

FERC was unwilling to approve several of PJM's proposed mechanisms for controlling or serving these loads, finding that portions appeared to intrude into areas traditionally controlled by the states, particularly retail electricity service.

But the Commission allowed the basic information architecture to remain.

Large loads can now be formally identified and tracked.

Commissioner David Rosner, who concurred with the decision, separately raised concern about a proposal that could have required IRAS customers to be curtailed before customers who had voluntarily joined traditional demand-response programs.

His concern illustrates the problem regulators are now trying to solve.

Once electricity demand becomes large enough, the question is no longer simply whether a business can connect to the grid.

It becomes a reliability question:

Who gets power when there is not enough for everyone?

Then there is the money

A separate DOE filing preserved in the repository addresses perhaps the most important issue for ordinary customers.

On October 7, DOE intervened in FERC Dockets ER26-3380-000 and EL26-108-000, concerning PJM's proposed Reliability Backstop Procurement.

DOE urged regulators to establish cost-allocation rules that prevent the infrastructure required for enormous new electricity users from being shifted onto existing customers.

That policy is straightforward:

If a new industrial-scale electricity customer requires new generation, new transmission infrastructure or other major grid investments, the customers creating that demand should bear those costs.

DOE summarized the concept as allowing large electricity users to build, bring or buy the capacity necessary to serve themselves.

This filing is easy to confuse with the IRAS proceeding because both involve PJM and large loads.

They are not the same case.

The October 7 DOE filing belongs to ER26-3380-000 / EL26-108-000.

The October 9 FERC order rejecting most of PJM's IRAS proposal belongs to ER26-3515-000.

The repository preserves both proceedings separately because combining them creates a misleading picture of what FERC approved, what it rejected, and what DOE is separately advocating.

Louisiana is already attached to this policy

Louisiana is not part of the PJM grid, so DOE Order No. 202-26-50 does not govern Louisiana utilities.

But Louisiana does appear in the broader federal policy surrounding the issue.

Governor Jeff Landry is a signatory to the Ratepayer Protection Pledge, introduced by the White House in March.

The pledge asks major technology companies and other participants in the data-center buildout to accept several commitments:

  • Build, bring or buy the new power required by their facilities.
  • Pay for the delivery infrastructure necessary to serve them.
  • Negotiate rate structures requiring them to pay for that infrastructure even if projected power consumption later falls.
  • Invest in local communities and workforce development.
  • Coordinate with grid operators so backup generation can contribute to grid reliability during shortages.

The repository's October 15 capture includes 324 entries on the White House signatory roster and preserves the underlying pledge documents.

The pledge itself is voluntary.

The more important development is that several of its principles are beginning to appear elsewhere in regulatory proceedings and emergency grid operations.

The philosophy is moving beyond a press release.

What Louisiana should watch

That makes the PJM proceedings relevant even hundreds of miles away.

Louisiana is in the middle of its own period of enormous industrial and data-center electricity development.

The important questions are becoming increasingly specific.

When a project requires hundreds of megawatts — or eventually gigawatts — of additional power, who finances the generation required to produce it?

Who pays for the transmission system necessary to deliver it?

What happens if the project requests enormous amounts of capacity and later consumes less electricity than projected?

Should those infrastructure costs eventually migrate into the rates paid by households and existing businesses?

Should enormous loads be required to disclose their expected electricity requirements through something resembling PJM's Large Load Registry?

And if the electric system reaches an emergency condition, should the substantial backup-generation fleets installed at large industrial campuses become available to support the wider grid?

Those are no longer speculative questions.

Federal regulators are already answering versions of them elsewhere.

The bigger story

The most significant part of these records may not be any individual DOE or FERC order.

It is the pattern.

First came concern about enormous new loads.

Then came proposals for tracking and managing them.

Then came explicit attempts to prevent their infrastructure costs from being shifted onto existing ratepayers.

Now an emergency federal order has demonstrated that backup generation located behind large loads can be incorporated into real-time reliability operations.

The policy debate around data centers is therefore changing.

The question is no longer simply:

How much electricity will they use?

It is becoming:

Who pays to build the system that serves them — and what obligations come with consuming that much power?

Those are questions Louisiana will eventually have to answer too.


Source Records

The complete DOE PJM Emergency Order / FERC IRAS / Ratepayer Protection Pledge collection is preserved in the 337.NEWS Louisiana Public Records Repository.

The collection includes DOE Order No. 202-26-50 and PJM's application and revised exhibits; FERC's October 9 order in ER26-3515-000 and Commissioner Rosner's concurrence; PJM's original 436-page IRAS proposal; DOE's filing in ER26-3380-000 / EL26-108-000; the Ratepayer Protection Pledge; and the October 15 signatory roster.

The repository also includes provenance records identifying the original government source, retrieval date and known gaps for each collection.

Editorial note: 337.NEWS is not affiliated with the U.S. Department of Energy, FERC, PJM Interconnection, the White House or any utility or company referenced in these records.

Author disclosure: Dalton Barron is a Louisiana real estate licensee affiliated with NextHome Bayou Pines. Views expressed by 337.NEWS are his own and do not represent NextHome Bayou Pines, its broker or affiliated offices. Licensed by the LREC. Each office independently owned and operated.