Entergy

21
Nov
Congress Says Data Centers Should Pay Their Own Way. Louisiana Has a $12.9 Billion Reason to Read the Fine Print.

Congress Says Data Centers Should Pay Their Own Way. Louisiana Has a $12.9 Billion Reason to Read the Fine Print.

The Senate passed a bill promising data centers will pay their own transmission costs. The fine print, and a $12.9 billion Entergy proposal in Louisiana, tell a more complicated story.
12 min read
18
Nov
Data Centers Can Avoid Millions in Electric Charges by Cutting Power for One Hour. Who Pays the Difference?

Data Centers Can Avoid Millions in Electric Charges by Cutting Power for One Hour. Who Pays the Difference?

A Texas data center could avoid $33.4 million in transmission charges by staying off the grid for one hour a year. Louisiana is building billions in power infrastructure for the same kind of customer. Who pays the difference?
8 min read
18
Nov
Entergy Wants to Buy a Texas Power Plant. Its Own Louisiana Regulators Say Data Centers Should Pay.

Entergy Wants to Buy a Texas Power Plant. Its Own Louisiana Regulators Say Data Centers Should Pay.

Entergy Louisiana wants approval to buy a 22-year-old Texas gas plant for about .8 billion and recover the cost from its customers. The commission's own staff consultant says the need is driven by Meta's data center, not general growth.
7 min read
21
Sep
Transmission tower and downed power lines near Lake Charles, Louisiana, following Hurricane Laura.

Entergy’s $600M Grid Plan Could Raise Bills — But Key Project Locations Aren’t Public

Entergy Louisiana wants approval for another $600 million in grid hardening. Customers could eventually pay more through the RPCR rider, while the locations and costs of seven transmission projects remain largely undisclosed.
8 min read