The AI Money Is Getting Nervous. Louisiana Is Still Building.

Lenders are repricing AI data-center debt, Goldman raised its AI spending forecast to $420 billion, and $260 billion in projects has been canceled. In Louisiana, Meta, Amazon, Hut 8, Applied Digital, Venture Global, and Azimuth are still building.
The AI Money Is Getting Nervous. Louisiana Is Still Building.
Server racks in a data center. Photo by Sergei Starostin, via Pexels. This is a generic stock image, not a photo of any Louisiana data center site named in this article.

337.NEWS | November 23, 2026

In one corner of the country, banks are trying to sell loans tied to data centers and discovering that buyers want a discount. In another, communities are stopping projects before the concrete arrives. Louisiana, meanwhile, is laying out the welcome mat, approving power infrastructure, negotiating decades-long arrangements, and attaching public incentives to developments whose buildings are supposed to last longer than the current excitement.

None of that proves the AI boom is over. The industry is still building, and lenders are still financing expensive deals. But the financial weather has changed, and Louisiana has a considerable amount of money, land, and public infrastructure standing outside in it.

A $300 million loan, offered below face value

Bloomberg reported November 16 that HSBC sold roughly $300 million in construction debt connected to a troubled New Mexico data center at prices in the mid-80 cents on the dollar. The loan formed part of a much larger $18 billion financing package for a campus in Doña Ana County, known as Project Jupiter, tied to Oracle and the Stargate AI initiative. The developer, BorderPlex Digital, reportedly received a force majeure notice weeks before the report, according to people familiar with the matter.

At 85 cents on the dollar, a holder accepting that price takes a roughly 15% discount to face value. It does not mean all $18 billion of the project's financing sold at that price. It does not prove a loan default. It means one lender chose to sell one exposure, on one project, at a discount. The rest of the lending syndicate was not reported to have done the same.

ING was also trying to move data-center debt. Reuters reported November 6 that the Dutch bank had offered approximately $500 million in loans through a competitive auction. The portfolio included a $25 million loan connected to a large New Mexico campus, along with debt tied to operators including Vantage Data Centers and CyrusOne. Bloomberg Law reported November 20 that the auction did not clear at acceptable prices; ING was reportedly working on individual sales instead.

There is a difference between a bank dumping every AI loan it owns and banks discovering that some buyers now demand a better price. These reports support the second conclusion. That's enough to matter.

Investors want more debt while lenders ask harder questions

The arithmetic gets uncomfortable when the demand for fresh borrowing rises at the same time lenders are becoming more selective.

According to a Reuters report published November 9, citing Goldman Sachs Research, global hyperscaler debt issuance could reach $420 billion in 2027, more than 60% above an estimated $250 billion for fiscal 2026. Expressed as an increase from those two rounded numbers, that is 68%. The figures are a projection, not a bill already run up.

A separate Goldman Sachs Exchanges discussion published August 5, 2026, put other parts of the financing market into context. Hyperscalers had issued roughly $108 billion in global debt in 2025 and $194 billion so far in 2026 at the time of recording. Goldman also tracked almost $500 billion in AI-related issuance year to date, with hyperscalers accounting for only about 40% of that. Goldman expected roughly $300 billion of project finance and data-center transactions in 2027, beyond direct issuance by hyperscalers. Those numbers describe different categories and reporting dates; adding or treating them as identical would be misleading.

The bank's analysts were not announcing a credit shutdown. They were describing a market in which investors want more compensation for certain risks. The spread on 10-year hyperscaler debt had reportedly widened by about 50 basis points year to date, versus about 20 basis points for high-quality industrial debt not linked to AI, according to a Bank of America analyst cited by Reuters. Insurance companies and other large investors had reportedly cut their participation in some long-dated AI financings by about half between early quarters of 2026, as Reuters described it.

The questions lenders are asking are mundane and devastatingly important: Who pays if the campus is delayed? Can the tenant reduce or terminate its commitment? What happens if promised hardware is obsolete before it arrives? Does a project have real cash flow, or only a convincing slide deck?

Financing has certainly not stopped. Reuters reported November 20 that Apollo and Goldman Sachs had priced approximately $44 billion in senior and subordinated notes supporting the purchase of GPUs and other equipment for SpaceX, in what the report described as the largest GPU financing to date. The financing was oversubscribed and upsized; investors included accounts linked to BlackRock, Goldman Sachs Asset Management, and KKR advisers. Equipment delivery was expected in the first half of 2027.

The picture is not a frozen lending market. It's a sorting process. Some giant deals get done. Some troubled or harder-to-value debt gets marked down.

What does “$260 billion canceled” actually mean?

Heatmap Pro reported on October 6, 2026, that at least $260 billion in planned U.S. data-center investment had been canceled during 2026 amid sustained local opposition. Roughly $130 billion of that, according to Heatmap, fell in the third quarter.

That is money announced for projects that did not proceed, not money already spent, evaporated, or written off. The original report assembled its estimates from public officials, local reporting, and regulatory materials. Heatmap said the estimate was likely incomplete because many projects do not publish investment values. It did not provide, in the material reviewed for this article, a project-by-project accounting allowing us to independently reconcile every dollar or distinguish every withdrawal from every delay.

Another tracker, Data Center Watch, counted at least 75 projects blocked or delayed with about $130 billion in associated investment during the first quarter of 2026. Those figures use different definitions and periods. Do not add them to Heatmap's total. They are two views of local resistance, not two piles of canceled cash.

A county in Virginia made Amazon change plans

Loudoun County sits in the middle of America's largest data-center concentration. If there is a place where the industry expects to have its way, this is a reasonable candidate.

Earlier in 2026, Amazon Web Services paid approximately $427.3 million for a 122-acre campus at George Washington University Virginia Science and Technology Campus in Ashburn. It planned four buildings totaling more than 800,000 square feet, called Bridgefield Tech Center.

Then the county took a different direction. On October 20, 2026, the Loudoun County Board of Supervisors voted on measures aimed at eliminating data-center uses on that campus. Two days later, Loudoun County announced a preliminary agreement with Amazon. Under the terms described by the county, Amazon would convey approximately 25 acres valued at $65 million and donate $5 million to the county's housing trust fund. The county would pursue accelerated rezoning for the remaining 97 acres, aiming for homes, a public school, and facilities for recreation, arts, and community use. The university would continue operating there for another four and a half years.

The agreement remained preliminary, and future housing construction was not guaranteed by the announcement. But the company did abandon the data-center proposal for that specific campus after buying the land. It did not abandon the data-center business, and the county did not obtain a verified guarantee that every dollar or acre would be used exactly as residents might hope.

In Caledonia, Wisconsin, Microsoft withdrew a different proposal before local officials voted. Its Project Nova application involved a 244-acre site west of the WE Energies Oak Creek coal power plant. According to local reporting, the company withdrew its October 2025 application after residents objected. Microsoft's statement cited community feedback and said it remained committed to investing elsewhere in southeast Wisconsin. No dollar value for Project Nova was verified in the draft's source material.

On November 3, 2026, voters in Sunbury, Ohio, approved a city-charter amendment restricting data centers with aggregate monthly energy demand or peak load exceeding 25 megawatts. The vote was 2,809 to 763, according to the local result reported in the draft. It followed an earlier city council moratorium that paused reviews. A moratorium is a pause; a voter-approved charter restriction is something more durable. The source material did not determine whether Sunbury's amendment blocks any previously vested project.

Other communities have pushed back too. In San Marcos, Texas, the City Council voted 5-2 in February 2026 to deny rezoning for a proposed $1.5 billion, 199.49-acre data center at 904 Francis Harris Lane, though the applicant could pursue another request under applicable procedures. A Columbus Dispatch report said at least 18 Ohio municipalities approved data-center bans or restrictions on November 3, with multiple additional proposals on ballots.

None of these examples means every community opposed to a project will win. They do demonstrate that an announced investment is not the same thing as a completed development, and that local decisions still have consequences.

Louisiana's ledger: some sites are building; others remain promises

The national reversals make for an easy headline. The harder job is looking at Louisiana's actual commitments without confusing a permitted site, an option on land, and a fully financed construction project.

The October 12 Industry Report identified four large Louisiana data-center projects under construction as of October 2026, representing more than $81.6 billion in announced planned investment. That's not $81.6 billion already spent. Ownership, power supply, financing, tax arrangements, and stages of completion differ project to project. Two additional sites described below were not at the same construction stage.

Meta's Hyperion, Richland Parish: under construction

Meta announced the 2,250-acre Franklin Farm campus in December 2024 with an investment exceeding $10 billion. In October 2025, it announced a joint venture with Blue Owl Capital to develop and own the campus. Blue Owl funds own 80%, Meta 20%. The arrangement includes capital contributions, a Meta operating lease, and options and obligations depending on future conditions. In July 2026, Meta announced plans to expand to 5 gigawatts of compute capacity, describing more than $50 billion of investment in the Richland Parish region, more than 7,500 peak construction jobs, and roughly 1,000 jobs when operational. The company said buildout would not be complete until the 2030s.

Meta also described a pledged $1 billion for local infrastructure improvements, including roads and water and wastewater systems, and reported more than $1.6 billion already contracted with local companies. The earlier $27 billion Blue Owl venture figure is part of the expanded project structure, not an additional $27 billion to stack on top of every later project announcement.

Power is the difficult part. The Louisiana Public Service Commission approved the first-phase Laidley Project in August 2025, encompassing three combined-cycle natural-gas plants totaling 2,262 megawatts at Richland Parish and the Waterford site in St. Charles Parish, plus approximately 1,500 megawatts of solar. Entergy began construction on the first Richland Parish plant in December 2025.

Entergy subsequently proposed a second phase of seven additional gas plants totaling more than 5,200 megawatts, with new transmission and battery storage, at an estimated $21.37 billion in capital value. That phase was still pending in the draft reviewed here, with an LPSC vote scheduled for December 16, 2026. The commission's fast-track Lightning Directive has itself drawn legal objections concerning procedure, not a finding on the merits of the power plants.

Entergy and Meta have said Meta will pay the full cost of the energy, water, and related infrastructure used by the data centers, and projected $2.65 billion in savings for Louisiana customers over 20 years. That is the companies' projection, not independently established savings already delivered to ratepayers.

Cost estimates have also moved. Gulf States Newsroom reported that the Waterford 5 gas plant was projected to cost $1.755 billion, up approximately 63% from Entergy's original $1.079 billion estimate. Other plant estimates moved in different directions. Who ultimately absorbs specific overruns depends on contracts and regulator decisions, not campaign slogans.

Transmission is another pressure point. Entergy reported acquiring 41 of 320 needed right-of-way tracts for transmission work as of November 2026. Landowners along the proposed Mount Olive-to-Sarepta corridor in north Louisiana have challenged acquisition efforts, and Entergy filed an expropriation suit in Lincoln Parish in October 2026. Regulatory allocations described in the draft included at least $470 million in infrastructure for which ratepayers could be responsible, while Meta would fund other substations and lines, according to Gulf States Newsroom. Those allocations remain subject to the relevant orders and agreements.

Amazon and STACK, Caddo and Bossier parishes: under construction

Amazon announced $12 billion in planned data-center investment in northwest Louisiana on February 23, 2026, with 540 direct jobs and an estimated 1,700 indirect jobs. The sites include locations in Caddo and Bossier parishes. Amazon's partner STACK Infrastructure is the developer and owner of the campuses. Amazon also committed $400 million toward public water infrastructure, according to the state's announcement.

In August, Amazon raised the announced investment to $18 billion, adding a third campus at Resilient Technology Park in Shreveport. The sites fall in SWEPCO's service territory, not Entergy Louisiana's. STACK said all three were under construction, aiming for first buildings by mid-to-late 2027 and full campuses around 2029. No public financing filing examined for the draft disclosed the debt/equity mix behind STACK's developments.

Hut 8 River Bend, West Feliciana Parish: under construction

Hut 8 announced in December 2025 that it would develop an AI campus near St. Francisville, with up to $10 billion in Phase I investment. The initial plan described 245 megawatts of critical IT load for Fluidstack, whose obligations were backed by a Google financial guarantee. Entergy Louisiana would provide an initial 330 megawatts of utility capacity. The announcement projected about 1,000 construction workers at peak and 75 permanent jobs initially. Later reporting discussed up to 200 permanent roles. The projected operation date was the second quarter of 2027.

A multibillion-dollar headline and a few dozen permanent jobs can coexist in the same project. That's why capital investment figures alone are not a sufficient measure of public return.

Applied Digital Delta Forge 1, Rapides Parish: under construction, power approval pending

Applied Digital broke ground in January 2026 on Delta Forge 1 near Boyce. The announced $3.6 billion campus spans approximately 300 acres, with 430 megawatts of utility power and 300 megawatts of critical IT load. Early operations were targeted for mid-2027, with approximately 200 direct jobs and more than 1,000 construction jobs at peak.

On June 23, 2026, Cleco filed for commission approval of a large-load contract, bridge capacity, transmission interconnection, and a planned 756-megawatt natural-gas plant. The plant approval remained pending in the source material, with a commission ruling sought by March 2027. Delta Forge qualified for Louisiana's data-center sales and use tax exemption under Act 730 of 2024.

Venture Global, Cameron Parish: application stage, not a completed campus

On October 15, 2026, LDEQ received air-permit applications for Cameron Campus Data Center No. 1, filed by Cameron Generation LLC, for a proposed development south of Cameron on the east side of the Calcasieu Ship Channel. The proposal described ten data-center buildings and two generating facilities. Administrative completeness is not construction approval; technical review was underway in the draft.

No verified Cameron-specific construction budget, output capacity, water use, or emissions estimate was established in the reporting reviewed. Venture Global separately announced framework agreements involving GE Vernova and Baker Hughes with a potential aggregate equipment value of up to $17.2 billion. That is a company-wide framework figure, conditional on proceeding, not a price tag for the Cameron proposal.

Azimuth Renewables, Moss Bluff: land option and evaluation

Azimuth Renewables of St. Louis signed an option in April 2026 to purchase more than 1,100 acres north of Coffey Road between Paul White Road and North Perkins Ferry Road in Moss Bluff. The company said in September it was evaluating whether a data-center project would work there. No operator, electrical demand, project footprint, schedule, or cost had been announced, and parish officials reported no rezoning or variance application.

Optioned land is not a construction site. It is a location someone may choose to develop, subject to a great deal that has not happened yet.

Louisiana has imposed pauses, but not the same kind of cancellation

New Orleans City Council adopted a one-year ban on data-center development through an interim zoning district on January 28, 2026, while its planning staff drafted rules. In Caddo Parish, a proposed two-year moratorium was deferred in committee in August 2026, and no enacted moratorium was identified in the reporting reviewed.

The LPSC is still writing rules for private-use electrical networks, including large-load self-supply proposals. It deferred consideration of a final plan in November to December 16, 2026. A proposed regulatory framework is not yet a final grant of expropriation authority.

No Louisiana data-center project among those reviewed for this article was verified as canceled, delayed, or withdrawn in the way the national examples were. That could change. It is not evidence that every Louisiana announcement will finish on time.

The bill comes due long after the ribbon cutting

The national credit-market reports have not linked the specific HSBC or ING loans to any of the Louisiana developments described above. Meta's Richland Parish campus, Amazon/STACK's northwest Louisiana campuses, Hut 8's River Bend, and Applied Digital's Delta Forge 1 have different counterparties, funding structures, and operating arrangements. This article does not suggest that one New Mexico loan discount proves a Louisiana borrower is in trouble.

The point is the duration of the commitments. Louisiana is making decisions about power plants that could run for decades, transmission corridors crossing private property, water and road infrastructure, and tax treatment lasting 20 years for qualifying facilities under Act 730. A developer's financing may be refinanced or restructured well before those commitments end. Meta's agreements involve a long project timeline and lease structure; Entergy's proposed second-phase power contract has been described as a 20-year arrangement. These are not interchangeable obligations, but they all deserve public scrutiny.

If a campus is delayed, who still pays for the line to it? If an operator never fills the buildings, who owns the stranded equipment? If the power plant costs more than forecast, what does the regulator allow the utility to recover? If the tax break outlives the jobs, who accounts for the difference? The answers live in commission filings, incentive agreements, land records, and contracts, not in an investor presentation about the future.

People in Louisiana have been told about billions in investment, thousands of construction jobs, and the arrival of an entirely new industry. Some of that work is already under construction. Some remains permit applications and land options. The banks financing this sector have begun making finer distinctions between those realities.

Louisiana should be making at least the same distinctions before the next right-of-way is taken, tax incentive approved, or long-term bill passed to customers.

What to watch next

  • December 16, 2026: Scheduled LPSC consideration of Entergy Louisiana's seven-plant Evest application, Docket U-37882, and the private-use electrical-network rulemaking, Docket R-37905. Confirm agendas before the meeting.
  • March 2027: Cleco's requested commission decision timeline for the Delta Forge 1 power-supply application.
  • January 31, 2027: Scheduled end of Sunbury, Ohio's earlier data-center moratorium, subject to the voter-approved charter amendment and later actions.
  • 2027 onward: Delivery and construction milestones for northwest Louisiana facilities, River Bend, Delta Forge, and the Meta campus.
  • ING loan sales: Whether reported individual transactions conclude, and at what prices. Those outcomes remained unresolved in the reporting reviewed.
  • Richland Parish transmission: Entergy's Mount Olive-to-Sarepta right-of-way acquisitions, litigation, and later regulatory cost allocations.

Sources and public records

Finance and cancellations

Community responses

Louisiana projects, utilities, and oversight

Reporting note: Announced capital investment is not spending already completed. Projections, regulatory requests, and preliminary agreements are labeled accordingly. No causal connection has been established between the HSBC or ING loans and Louisiana's listed projects.