6 min read

Venture Global Targets 2028 for Louisiana AI Data Centers as Private Power Plants Expand

Venture Global plans to begin supplying computing capacity for AI data centers as early as late 2028 or early 2029, using privately generated electricity at its sites in Cameron and Plaquemines parishes.
Venture Global Targets 2028 for Louisiana AI Data Centers as Private Power Plants Expand

Venture Global is moving closer to becoming something considerably bigger than an LNG exporter.

During its November 10 earnings call, the company laid out plans to begin supplying computing capacity for artificial intelligence data centers as early as late 2028 or early 2029, using privately generated electricity at its industrial sites in Cameron and Plaquemines parishes.

The announcement provides a clearer timeline for a development that has already surfaced in Louisiana's environmental permitting records.

It also reveals the scale of the company's ambitions.

Venture Global has entered agreements with GE Vernova and Baker Hughes for access to as many as 16 additional power-generation units, each rated at 720 megawatts.

Combined, those units represent a potential 11,520 megawatts, or 11.52 gigawatts, of generating capacity.

That is not a commitment to install all 16 units in Cameron Parish. The equipment agreements cover potential development across both Louisiana locations and allow the company to expand in stages.

Nevertheless, the magnitude of the proposal illustrates how far the company's plans extend beyond exporting natural gas.

The first data centers could arrive in 2028

Venture Global CEO Mike Sabel told investors that the company anticipates developing its computing facilities in increments of approximately 250 megawatts.

The company expects its first 250 megawatts of computing capacity to become operational in late 2028, with development accelerating through 2029 and 2030.

It has identified a target of approximately 5 gigawatts of computing capacity by the end of 2031, with the potential to reach 10 gigawatts by 2034.

Those targets cover Venture Global's proposed operations in Cameron and Plaquemines parishes combined. The company has not publicly established how much of that capacity will ultimately be located in each parish.

The first major equipment purchases could happen considerably sooner.

According to management's prepared remarks, Venture Global plans to order its first power plant before the end of 2026 and a second in early 2027.

Additional purchases would depend on securing customers for the proposed computing infrastructure.

These remain corporate development targets, not completed construction commitments or final regulatory approvals.

Louisiana already has the permit applications

The announcement is especially relevant because the proposed power-generation facilities are not merely theoretical.

Public notices from the Louisiana Department of Environmental Quality identify two separate facilities proposed by Cameron Generation LLC.

Both applications were received October 15, 2026.

Cameron Campus Data Center No. 1

The first application concerns a site south of Cameron, on the east side of the Calcasieu Ship Channel near the Gulf of Mexico.

Its regulatory identifiers include:

  • Agency Interest No. 241614
  • Title V permit application 0560-01000-V0
  • PSD permit application PSD-LA-860
  • Activities PER20260001 and PER20260002

Cameron Campus Data Center No. 2

The second application identifies property north of Marshall Street, east of Wakefield Road and the Calcasieu Ship Channel.

Its identifiers include:

  • Agency Interest No. 252617
  • Title V permit application 0560-01008-V0
  • PSD permit application PSD-LA-876
  • Activities PER20260001 and PER20260002

LDEQ determined both applications were administratively complete and identified them for expedited processing under Louisiana Administrative Code Title 33, Part I, Chapter 18.

Administrative completeness means regulators have determined that an application contains sufficient information to proceed with review.

It does not mean construction has been approved.

These applications involve facilities supporting data-center operations, particularly the generation of electricity required to power them.

The critical next step is to examine the underlying engineering and emissions documents against Venture Global's newly disclosed development schedule.

The company wants to generate its own electricity

One of the most significant aspects of Venture Global's proposal is its plan to operate independently of Louisiana's public electrical grid.

The company calls this an island-mode power system.

Rather than relying on an electric utility to supply hundreds or thousands of megawatts through the regional transmission network, Venture Global intends to generate electricity through its own industrial power infrastructure.

The company says this approach could allow it to develop large data centers more quickly than projects waiting for conventional utility interconnections.

Venture Global also says its proposed facilities would not rely on public water supplies.

That could address two major concerns surrounding data-center development: electricity costs and competition for public water infrastructure.

But producing electricity privately does not eliminate the environmental consequences of producing it.

Large natural-gas-fired generating facilities still require fuel, combustion equipment, emissions controls, cooling systems, maintenance infrastructure and applicable regulatory authorizations.

The questions change from how much electricity a data center will draw from the public grid to what must be built to generate that electricity independently.

That is precisely why the environmental permit applications deserve attention.

What does 11.52 gigawatts actually mean?

The company's agreements concern up to 16 generating units capable of producing 720 megawatts apiece.

That represents an enormous potential industrial power-development program.

However, several numbers must be kept separate.

The 11.52-gigawatt figure represents the combined generating capacity of equipment covered by the agreements, not generating capacity already installed.

The 5-gigawatt target for 2031 concerns the company's planned computing capacity across its two Louisiana sites.

And neither figure establishes that all proposed facilities will be constructed, financed, occupied by customers, or approved by regulators.

Venture Global has described a phased business strategy intended to align construction with customer commitments.

Its existing LNG operations provide the industrial foundation for that expansion.

In its November earnings disclosure, the company reported approximately 15,000 acres of controlled land, access to roughly 13 billion cubic feet per day of pipeline capacity, and approximately 4 gigawatts of existing power infrastructure across its operations.

Those resources could give the company an advantage in developing privately powered data centers.

But they also raise questions about the cumulative industrial footprint of LNG production, electricity generation, and computing facilities operating near one another.

The economics are becoming clearer

Venture Global reported approximately $4.8 billion in third-quarter revenue and $2.5 billion in net income.

The company also increased its forecast for full-year adjusted earnings before interest, taxes, depreciation and amortization to between $10 billion and $10.3 billion.

Those financial results help explain why Venture Global believes it can expand into data centers while continuing to develop its LNG business.

The company expects production at its CP2 LNG project in Cameron Parish to begin around the middle of 2027.

It is also targeting an early 2027 final investment decision for a proposed 10-million-metric-ton-per-year CP2 expansion, with production potentially beginning in late 2028.

That places multiple major industrial development timelines in Cameron Parish within roughly the same period.

What Cameron Parish residents still need to know

The new corporate disclosures answer some important questions about timing and business strategy.

They do not answer everything about the environmental and local consequences.

The public still needs to know how many generating units will ultimately be installed in Cameron Parish, how much natural gas those units will consume, and what emissions the facilities will be permitted to release.

The final design of the private electrical network, its cooling and water requirements, and any associated pipeline construction also deserve scrutiny.

There is another question surrounding the economic benefits.

Will these facilities create substantial permanent local employment, or will most of the investment be concentrated in equipment, construction, electricity generation and computing hardware?

A project can involve billions of dollars without producing an equivalent increase in long-term local jobs.

Those figures need to be examined as the development progresses.

The larger change underway

Venture Global entered Louisiana's industrial landscape as a developer of liquefied natural gas export terminals.

It is now describing a business that could combine natural gas infrastructure, private electricity generation, industrial land and artificial intelligence computing facilities.

The company has characterized that strategy as the development of a vertically integrated AI utility.

For Louisiana, this represents another step toward industrial projects that control much of their own supporting infrastructure.

That business model could reduce pressure on public utility systems while raising new regulatory questions about private power generation, cumulative emissions, land use and environmental oversight.

The November announcement does not mean Cameron Parish has approved an 11.52-gigawatt development. It means a major industrial operator has disclosed plans to pursue that scale of generating equipment, and Louisiana already has air-permit applications associated with its emerging data-center operations.

The next test will be what regulators authorize, what Venture Global actually builds, and how closely those decisions match what the public has been told.


Sources and public records

  1. Venture Global: Third Quarter 2026 Financial Results, November 10
  2. Venture Global: November 10 Earnings Call Prepared Remarks
  3. Venture Global SEC-filed Third Quarter Earnings Release
  4. LDEQ Administrative Completeness Notice: Cameron Campus Data Center No. 1
  5. LDEQ Administrative Completeness Notice: Cameron Campus Data Center No. 2
  6. Louisiana Department of Environmental Quality: Public Notices
  7. 337.NEWS Louisiana Public Records Repository

Reporting note: Corporate projections and proposed equipment capacities are identified separately from regulatory approvals. The LDEQ notices establish receipt and administrative completeness of the applications, not issuance of final permits. This report does not claim that the underlying air-permit engineering attachments were independently reviewed.

Photo: Industrial gas storage sphere. Photo by Jan van der Wolf, via Pexels.

337.NEWS discussion

Join the conversation.

Sign up to comment on this story and follow the local reporting behind it.